Production schedule for the 40/50 HP Chassis T2 Series, outlining quantities, output, and key milestone dates.


Identifier  ExFiles\Box 142\2\  scan0287
Date  2nd May 1934
  
ROY {Mr H. Royce - Buyer} 4/MG2.5.34

40/50 HP. CHASSIS - T2.SERIES
7039-7138

Number of Chassis in Series ......... 100

Proposed Output .................... 4 per week
(including holidays)

Authority to proceed given ......... 50 - Wor {Arthur Wormald - General Works Manager} 2/R7.4.34
50 - Wor {Arthur Wormald - General Works Manager} 1/R20.4.34

First Chassis to be sent to test
week commencing ...... October 8th.1934

Drawing Office to complete issue of
instructions week ending ... 50 - April 12th.1934
50 - April 28th.1934

ORDER OFFICE TO COMPLETE ISSUE OF ORDERS:

Class D (Forging Bars and Billets) ... May 5th.1934
Classes C & D and any materials
required from overseas ...... May 12th. "
Class B .......................... May 19th. "
Class A .......................... May 26th. "
Instruments ...................... May 26th. "

Material to be in Stores:

Class D (Forging Bars and Billets) ... June 23rd "
Classes C & D ...................... July 3rd "
Class B .......................... July 21st "
Class A .......................... August 4th "
Instruments ...................... August 4th "

Material to be issued to Works, together
with instructions and production cards:

Castings made in our Foundry, and
Forgings produced in our Drop Forge ... June 30th. "
Classes C & D ...................... July 21st "
Class B .......................... August 4th "
Class A .......................... August 18th.
Instruments ...................... September 1st.
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙