The temporary suspension of work on a tool box due to insufficient information.


Identifier  ExFiles\Box 175\3\  img257
Date  4th November 1940
  
To Rm. {William Robotham - Chief Engineer} from Rm {William Robotham - Chief Engineer} /HH.
c.c. Rm {William Robotham - Chief Engineer} /SWF.

Rm {William Robotham - Chief Engineer} /HH.1/SW.4.11.40. 3

I have temporarily held up work in connection with the tool box on account of insufficient information.

As one attempt has been made to produce this box, a further attempt seems futile until we are sure of the contents of the tool kit.

The outstanding parts are as follows :-

Definite information of the barrel brush (complete with handle). Rm {William Robotham - Chief Engineer} /CTS {C. Trot Salt - Carburation} has this job in hand.

1 gallon Liquid container (Littleover are dealing with this matter.

Admiralty spanners to replace Rolls-Royce jaw spanners (Rm {William Robotham - Chief Engineer} /CTS {C. Trot Salt - Carburation} has promised to progress this item).

Clearing tool and handle (This is in the Design stage at Littleover).

Since these points are at present in the air, I propose to wait until we are supplied with some definite information.

Rm {William Robotham - Chief Engineer} /HH. HeHc
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙