Progress report for the Mark 6 A.15 Tank Leyland Meteor engine.


Identifier  ExFiles\Box 133\4\  scan0232
Date  3rd February 1941
  
-2-
Ev. {Ivan Evernden - coachwork} 5/JH.3.2.41.

Progress Report - Feb. 3rd. 1941.
Tank Section.
Mark 6 A.15 Tank Leyland Meteor.

Work Completed.

PL.498 Squint Hole for Timing Pointer. Stage la. {L. A. Archer} & lb.
PL.499 Limiting Features re design of 16 in. dia. Borg & Beck Clutch. Stage III.
PL.551 R.H. Water Inlet Pipe. Stage la. {L. A. Archer} lb.
PL.552 L.H. Water Inlet Pipe. Stage la. {L. A. Archer} lb.
PL.553 Compressor & Drive. Stage la. {L. A. Archer}
PL.554 Oil Relief Valve & Main Feed Pipe. Stage la {L. A. Archer} only.
PL.555 Cooling system, petrol and oil tanks (Rm {William Robotham - Chief Engineer} /FJH {Fred J. Hardy - Chief Dev. Engineer} ). Stage 3.
PL.556 Mod. Exhaust Manifold. Stage la {L. A. Archer} & lb.
PL.557 Oil Gallery & Relief valve. Stage lb only.
PL.558 Compressor Drives. Stage lb.

Work in Hand.

Cast Iron Crankcase Detail. Stage lb. 60%
Rear end of crankcase & Engine Coupling. Stage lb 10%
PL.559 Cylinder Head with 2 plugs on Inlet Side. Stage lb. 90%
Cylinder Block for Head with 2 plugs on inlet side. Stage lb. 90%
Space available for air cleaner. Stage la. {L. A. Archer} & lb 90%
Gearbox gears & Shafts 6.750 ins. centres. Stage 3 in hand.
Project of Controll Epicyclic Steering. Stage 3 in hand.
Engine Bearer Arms and Oil Piping. Stage lb 60%
Wiring Harness in Vee. Stage lb in hand.
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙