Works chart showing the planned weekly chassis output for the Phantom III model from August to December 1937.

Identifier  ExFiles\Box 91\1\  scan0514
Date  9th August 1937
  
Rm{William Robotham - Chief Engineer}
300
WORKS CHART.
Chart No. 164.
RHC{R. H. Coverley - Production Engineer}/JMV.3/EMG.9.8.37.
CHASSIS OUTPUT.
PHANTOM III CHASSIS.
OUTPUT FROM ERECTING BAY TO TEST DEPT.
Below we give you particulars of the programme to be worked to up to the end of December. This cancels all previous charts:-
1937.
Week-ending. Weekly Output. Position on Series.
Aug. 14th 6 C.117
21st 5 122
28th 4 126
Sept. 4th 4 130
11th 4 134
18th 4 138
25th 4 142
Oct. 2nd 3 145 September Holiday.
9th 4 149
16th 4 153
23rd 4 157
30th 4 161
Nov. 6th 4 165
13th 4 169
20th 4 173
27th 4 177
Dec. 4th 4 181
11th 4 185
18th 4 189
25th 4 193
  
  