From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Works chart showing the planned weekly chassis output for the Phantom III model from August to December 1937.
Identifier | ExFiles\Box 91\1\ scan0514 | |
Date | 9th August 1937 | |
Rm{William Robotham - Chief Engineer} 300 WORKS CHART. Chart No. 164. RHC{R. H. Coverley - Production Engineer}/JMV.3/EMG.9.8.37. CHASSIS OUTPUT. PHANTOM III CHASSIS. OUTPUT FROM ERECTING BAY TO TEST DEPT. Below we give you particulars of the programme to be worked to up to the end of December. This cancels all previous charts:- 1937. Week-ending. Weekly Output. Position on Series. Aug. 14th 6 C.117 21st 5 122 28th 4 126 Sept. 4th 4 130 11th 4 134 18th 4 138 25th 4 142 Oct. 2nd 3 145 September Holiday. 9th 4 149 16th 4 153 23rd 4 157 30th 4 161 Nov. 6th 4 165 13th 4 169 20th 4 173 27th 4 177 Dec. 4th 4 181 11th 4 185 18th 4 189 25th 4 193 | ||