Outlining the timeline for the production of higher lift cams for a P.2. model.
| Identifier | ExFiles\Box 13\2\ 02-page070 | |
| Date | 27th May 1931 | |
| E c. Eg. c. Wor. {Arthur Wormald - General Works Manager} c. Hs. {Lord Ernest Hives - Chair} c. RHC. {R. H. Coverley - Production Engineer} 8709D BY15/C.27.5.31. RE: HIGHER LIFT CAMS FOR P.2. --------------------------- With reference to E2/M23.5.31. we have discussed this matter with RHC. {R. H. Coverley - Production Engineer} , and he states that it would take about 10 days from receipt of drawings in which to produce the cam forms. The calculations and drawings would take 4 days, so that the actual forms should be available in 14 days from instructions to proceed. BY. {R.W. Bailey - Chief Engineer} BM | ||