From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Cost estimation for new tools relating to the standardisation of parts for the Phantom III 'E' Series chassis.
Identifier | ExFiles\Box 115\1\ scan0369 | |
Date | 15th March 1938 | |
PHANTOM III STANDARDISATION OF PARTS RR Ltd. (H.o) 8548 10-2-36 WHW Ltd. Table 1: Date: 15.3.38 Drawing No.: X.1050. Estimated cost of new tools £15. 0. 0. Could be brought on to production at the 1st chassis in "E" Series (without scrap) Table 2 (Cost analysis): Headers: MATERIAL, LABOUR, CHARGES, TOTAL Sub-headers: s., d.{John DeLooze - Company Secretary} Row 1 (Cost of Old Part): CHARGES: 3 6, TOTAL: 11 3 Row 2 (Cost of New Part): TOTAL: 2 2 Row 3 (Nett Increase): CHARGES: 7 Row 4 (Decrease): TOTAL: 2 10 Summary line: 9s. 2d. Signature of Chief Cost Dept. that above is correct. Table 3 (Approval): Headers: INITIAL, DATE, REMARKS Initials: SE, WS, E, AG, BY, EB, RHC{R. H. Coverley - Production Engineer}, XM, MW | ||