Production status of 20/25 HP 'W' Series chassis material, noting holds on certain parts.
| Identifier | ExFiles\Box 142\2\ scan0157 | |
| Date | 8th August 1932 | |
| By. {R.W. Bailey - Chief Engineer} Roy. {Mr H. Royce - Buyer} Sft. {Mr Swift} c. Hs. {Lord Ernest Hives - Chair} RECEIVED 12 AUG X 4554. Wor. {Arthur Wormald - General Works Manager} Absent. Hy {Tom Haldenby - Plant Engineer} 3/GR. {George Ratcliffe} 8.8.32. 20/25 H.P. CHASSIS MATERIAL. Hy {Tom Haldenby - Plant Engineer} 2/T22.7.32. *W* Series. The position of this series is now as under:- 1st 50 sets to be exactly similar to 'V'. 2nd 50 " " " " " " except exhaust system material is to be held up. 2nd 100 " material on order are subject to exhaust system and side frames being held up. Hy. {Tom Haldenby - Plant Engineer} | ||
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).