Production programme and parts list for the 'Myth' body, detailing timelines and components.

Identifier  ExFiles\Box 117\3\  scan0304
Date  14th February 1941
  
-6-

Cont'd.{John DeLooze - Company Secretary}

use the following parts of the saloon for this body with slight modifications, which will be made by hand. Floor, front end from door opening; sills; rear wings?; front seats.

The special parts which will be made by hand are :-

Doors, Tonneau panels including trunk, folding hood and windscreen; rear wings depending on selected design.

PROGRAMME FOR MYTH BODY

The time required to prepare for production after the prototype has been tested and approved is as follows :-

12 Months
( Detail Drawings.
( Press Tools.
( Preliminary Specification.
( Sample Materials & Fittings.
( Shop Layout & Equipment partly installed.
( Sample Body Shell in White.
Production Cars 18 Months.

6 Months
( Complete Specifications.
( Upholstery Patterns.
( Jigs & Templates.
( Equipment fully installed.

If the prototype is not built now, it will take at least an additional 6 months.
  
  