Production schedule and timeline for the Bentley 'K' series chassis.

Identifier  ExFiles\Box 142\2\  scan0372
Date  7th August 1936
  
ROY{Sir Henry Royce}7/MG7.8.36

BENTLEY CHASSIS - "K" SERIES

K-A 1801-1900
K-B 1901-2000

Number of Chassis in Series ............. 200
Proposed Output ........................ 12 per week (including holidays)
Authority to proceed ................... Hyl/H30.7.36
First Chassis to be sent to test week commencing ...... Feb. 15th.1937
Drawing Office to complete issue of instructions week ending .. Aug. 8th.1936

ORDER OFFICE TO COMPLETE ISSUE OF ORDERS:
Class D (Forging Bars & Billets) ........ On order.
Classes C & D, and any materials required from overseas .... Aug. 15th.1936
Class B ................................ Aug. 22nd. "
Class A ................................ Aug. 29th. "
Instruments ............................ Sept. 5th. "

Material to be in Stores:
Class D (Forging Bars & Billets) ....... Oct. 24th.1936
Classes C & D .......................... Nov. 7th. "
Class B ................................ Nov. 21st. "
Class A ................................ Dec. 5th. "
Instruments ............................ Dec. 19th. "

Material to be issued to Works, together with instructions and production cards:
Castings made in our Foundry, and Forgings produced in our Drop Forge .... Oct. 31st.1936
Classes C & D .......................... Nov. 21st. "
Class B ................................ Dec. 5th. "
Class A ................................ Dec. 19th. "
Instruments ............................ Jan. 2nd. "
  
  