Drawing office progress on the Ripplet specification.
| Identifier | ExFiles\Box 118\1\ scan0103 | |
| Date | 28th February 1940 | |
| 1022. To HPS {Horace Percy Smith - Experimental Factory Mgr} /RH. {R. Hollingworth} from Rm. {William Robotham - Chief Engineer} Rm. {William Robotham - Chief Engineer} 3/MH. {M. Huckerby} 28.2.40. DRAWING OFFICE PROGRESS. We attach a copy of the covering sheet issued with the 2nd. issue of the Ripplet specification. We do not propose to issue a 3rd. specification, but attach the covering sheet which demonstrates progress made up to 28/2/40. You will note that the outstanding work to be done is now reduced to 3 items requiring detailing and 4 completion of designs. Rm. {William Robotham - Chief Engineer} | ||