From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Alteration to part G.73149, increasing its length from 3.00' to 4.00' to reduce front braking.
Identifier | ExFiles\Box 66\5\ scan0097 | |
Date | 9th December 1926 | |
RR 755 REVISED (10H) (DE444 6-10-26) BM. STANDARDISATION of CHASSIS PARTS. X 8420 COMPLETED. 25.1.27. Date 9.12.26 Description of Parts. ALTERATION TO G.73149. ORIGINAL LENGTH 3.00. PROPOSED LENGTH 4.00" Origin. To reduce front braking. Experimental Test Report. This alteration to the lever length reduces the percentage of braking to the front to 33%. The present front braking is 40% of the total. Road Test Report. This alteration is considered desirable to prevent the steering being affected when braking on corners. It can be applied retrospectively if considered desirable. X No. 8420 Drawing No. G.75413 Part List A Scrap and replace at all costs, including Chassis already delivered to Customers. B Scrap and replace on Chassis in Works. C Scrap present stock and replace on all Chassis not yet handed to test. D Use existing stock Alteration effective on future Chassis. Weight of Old Part. Weight of New Part. Difference per Car. Cost of Old Part. £ Cost of New Part. £ Difference per Car. £ Negligible. Signature from Cost Dept. that above is correct. My/Rb. {R. Bowen} 7.1.27 Cost of Parts in Works which will be scrapped if commenced on :- Series.........£...... Series.........£...... Series.........£...... INITIAL | DATE | REMARKS BJ. | 21.1.27 | Agreed BJ R. {Sir Henry Royce} | 12.12.26 | Agreed, FHR. New braking to front will be 3/4 change than I had imagined i.e. from 40% to 33% = 3/3.66 say 3 3/4. WOR. {Arthur Wormald - General Works Manager} | 9.12.26 | Agreed. Wor. {Arthur Wormald - General Works Manager} RG. {Mr Rowledge} | 9.12.26 | Agreed. Rg. {Mr Rowledge} DA. {Bernard Day - Chassis Design} | 11.12.26 | Agreed. Da. {Bernard Day - Chassis Design} BY. {R.W. Bailey - Chief Engineer} | 10.12.26 | Agreed. BY. {R.W. Bailey - Chief Engineer} EP. {G. Eric Platford - Chief Quality Engineer} | 11.12.26 | Agreed. EP. {G. Eric Platford - Chief Quality Engineer} E. {Mr Elliott - Chief Engineer} | 12.12.26 | Agreed. E. {Mr Elliott - Chief Engineer} PN. {Mr Northey} | | CWB. | 19.1.27 | Agreed. CWB. Hs. {Lord Ernest Hives - Chair} | 9.12.26 | Agreed. Hs. {Lord Ernest Hives - Chair} | ||