Progress report from April 1940 detailing the status of various engineering projects and work in hand.

Identifier  ExFiles\Box 133\4\  scan0158
Date  30th April 1940
  
Ev.{Ivan Evernden - coachwork}1/JH.30.4.40.

Progress Report - April 29th. 1940.

Work in Hand.

PL.35 1/4 scale layout of Rippletto. - Rippletto - in hand.
PL.159 Dynamo and Salt Water Pump - Marine 98%
PL.181 Plan of sump and reverse box joints - Marine - 75%
PL.182 Sandwich piece and reverse box - Marine - 75%
PL.198 Fresh and salt water and oil connections - Marine - 90%
PL.209 Connections for Vacuum for Column change - Senior Range 80%

Ignition Coil Mounting Marine 25%
Marine Induction Pipe Marine 90%
PL.207 Geometry of front wheels Bentley 6 80%
Revised tubular hand brake Senior Range 30%
Hydraulic master cylinder Rippletto 40%
Project of lockheed brakes (revised) Rippletto in hand.
Junior gearbox. Junior Range 85%
Project of Cadillac Gear Shift " " 50%
PL.205 Spring fixing for rear cross member in
Sheet metal - Senior Range - 80%

Rippletto frontal appearance Ripplet - in hand.
Spring test rig. Plant 50%
Details of PL.162 Plant - in hand.
PL.203 Radiator fan belt test rig. Plant - 90%

...................
  
  