Production programme and timeline for a prototype car body named 'Myth', detailing parts and required development stages.

Identifier  ExFiles\Box 144\2\  scan0031
Date  14th February 1941
  
-6-

Cont'd.{John DeLooze - Company Secretary}

use the following parts of the saloon for this body with slight modifications, which will be made by hand. Floor, front end from door opening; sills; rear wings?; front seats.

The special parts which will be made by hand are :-

Doors, Tonneau panels including trunk; folding hood and windscreen; rear wings depending on selected design.

PROGRAMME FOR MYTH BODY

The time required to prepare for production after the prototype has been tested and approved is as follows :-

( Detail Drawings. )
( Press Tools. )
( Preliminary Specification. )
12 Months ( Sample Materials & Fittings. )
( Shop Layout & Equipment partly )
( installed. )
( Sample Body Shell in White. ) Production Cars 18 Months.

( Complete Specifications. )
6 Months ( Upholstery Patterns. )
( Jigs & Templates. )
( Equipment fully installed. )

If the prototype is not built now, it will take at least an additional 6 months.
  
  