From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Supply schedule and issues with S.U. petrol pumps for the Phantom III frame.
Identifier | ExFiles\Box 149\4\ scan0319 | |
Date | 4th June 1937 | |
Hs.{Lord Ernest Hives - Chair} from Rm.{William Robotham - Chief Engineer} c. E.{Mr Elliott - Chief Engineer} c. By.{R.W. Bailey - Chief Engineer} 1263 Rm{William Robotham - Chief Engineer}4/R.4.6.37. S.U. PETROL PUMPS FOR FITTING IN P.III FRAME. Attached is a copy of a note from Dixon on his visit to S.U's. Briefly, we shall get the first 6 pumps in 10 days, the next 18 not earlier than a month from then, onwards 6/12 pumps per week if we order them forthwith. Skinner has definitely let us down on the 24 pumps by using the material which he had got in for 18 of them on another job. Rm.{William Robotham - Chief Engineer} | ||