Rolls-Royce Archives
         « Prev  Box Series  Next »        

From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Examination timeline for Delauney Belleville and Lanchester chassis.

Identifier  ExFiles\Box 22\3\  Scan039
Date  29th March 1912
  
R.R. 255A (100 B) (X590. 6.2.19) (G 936S

X440

EP{G. Eric Platford - Chief Quality Engineer}1/T28312.

Re Delaunay Belleville & Lanchester Chassis.

W to S.
Mr Owen.

29.3.12 C20/H27312 I cannot say with any degree of certainty when we shall have finished with the above.

Lanchester chassis is now dismantled for examination, and we are going to do the same with the Delaunay Belleville, and ^cannot hope to finish our investigations on this for at least 2 months and even this is only a very rough estimate.

E.P.

[Watermark: MADE AT CROXLEY]
  
  


Copyright Sustain 2025, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙