Examination timeline for Delauney Belleville and Lanchester chassis.
Identifier | ExFiles\Box 22\3\ Scan039 | |
Date | 29th March 1912 | |
R.R. 255A (100 B) (X590. 6.2.19) (G 936S X440 EP{G. Eric Platford - Chief Quality Engineer}1/T28312. Re Delaunay Belleville & Lanchester Chassis. W to S. Mr Owen. 29.3.12 C20/H27312 I cannot say with any degree of certainty when we shall have finished with the above. Lanchester chassis is now dismantled for examination, and we are going to do the same with the Delaunay Belleville, and ^cannot hope to finish our investigations on this for at least 2 months and even this is only a very rough estimate. E.P. [Watermark: MADE AT CROXLEY] | ||