Rolls-Royce Archives
         « Prev  Box Series  Next »        

From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Typed schedule of dates for chassis and body development and testing.

Identifier  ExFiles\Box 97\3\  scan0025
Date  4th January 1939
  
-2- Rml/R.4.1.39.

Therefore, tabulating the dates fixed we get the following:-

January 14th - all drawings to be in the hands of HPS.{Horace Percy Smith - Experimental Factory Mgr}

January 17th - Paulin completes full scale drawings of body, and hands to Van Vooren.

January 21st - Frame to be delivered.

February 19th- Chassis, complete with rear road springs, petrol tank, dashboard, steering column, and as many other parts as are available, handed over to Experimental Garage for despatch to France.

April 23rd. - Chassis returned, completed with body, from Van Voorens.

May 8th. - Car handed to Experimental Garage for preliminary tests prior to commencement of 15,000 miles Continental endurance.

We should like to have your opinion on this programme, because all we have tried to do is to allot the available time as fairly as possible to manufacturing and testing respectively.


Rm.{William Robotham - Chief Engineer}
  
  


Copyright Sustain 2025, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙