Production schedule for the 25/30 HP Chassis - P.2 Series, detailing output and timelines for materials and parts.
Identifier | ExFiles\Box 142\2\ scan0381 | |
Date | 24th November 1936 | |
ROY{Sir Henry Royce}5/MG24.11.36 25/30 HP. CHASSIS - P.2 SERIES P2-A.{Mr Adams} 7513-7612 P2-B. 7613-7712 Number of Chassis in Series .............. 200 Proposed Output .......................... 17 per week (including holidays) Authority to proceed ..................... Wor{Arthur Wormald - General Works Manager}5/R.7.10.36 First Chassis to be sent to test week commencing ........................ March 22nd.1937 Drawing Office to complete issue of instructions week ending ............ October 17th.1936 ORDER OFFICE TO COMPLETE ISSUE OF ORDERS:- Classes C & D and any materials required from overseas ........................ October 24th.1936 Class B ................................ October 31st. " Class A ................................ November 7th. " Instruments ............................ November 14th. " Material to be in Stores: Class D (Forging Bars & Billets) ......... December 12th.1936 Classes C & D ............................ December 26th. " Class B ................................ January 9th.1937 Class A ................................ January 23rd. " Instruments ............................ January 23rd. " Material to be issued to Works, together with Instructions and Production Cards: Castings made in our Foundry, and Forgings produced in our Drop Forge .......... December 19th.1936 Classes C & D ............................ January 9th.1937 Class B ................................ January 23rd. " Class A ................................ February 6th. " Instruments ............................ February 20th. " | ||