Costing and production details for sets of Whitemetal main bearings.

Identifier  ExFiles\Box 115\3\  scan0219
Date  2nd May 1938
  
1020.

Rm.{William Robotham - Chief Engineer} from Rm{William Robotham - Chief Engineer}/Swdl.{Len H. Swindell} Typed 2.5.38.

3 sets of Whitemetal main bearings without
shims were made.

1 set on W.III No.4. 27.G.VI.
1 set on B.III No.2.

1st. set officially ordered by us is for B.III
No.3 unit.

Approx. cost of producing above per set of
bearings.

Material Labour Total + 200% Labour
5.066 9.801 34.5

Actual fitting of bearings in crankcase approx.
12 hours work for 1 man say

25s. + 50s (200%) = 75s.

Taking into account forming of bearing without
shims would say a total of 125s.
  
  