From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Implementation of a new standardized chassis part, its costs, and the chassis series it applies to.
Identifier | ExFiles\Box 14\4\ Scan090 | |
Date | 17th December 1928 | |
Header (reversed): STANDARDISATION of CHASSIS PARTS Stamped Box: 3812 3813 X 3814 19 DEC 1928 20 DEC 1928 21 DEC 1928 24 DEC 1928 Main Content: The number of the first chassis on which the new part will be fitted. N.2. series. Date when chassis will be handed to test. ---- Cost of scrapped material, if any. Nil. Cost of jigs and tools. Approx. £365. Table: Column Headers: REASON | DATE | INITIALS Row 1: V.A-S | 17-12-28 | ROW Row 2: | | OF Row 3: | | AD Row 4: | | PS Row 5: | | EB Row 6: | | MS Row 7: | | CWB Row 8: | | HR | ||