Delay in the completion of drawings for tools for the Wraith Chassis.
Identifier | ExFiles\Box 6\6\ 06-page423 | |
Date | 21th January 1938 | |
Secret. 600 To H.I. & (Sm.) From RHC.{R. H. Coverley - Production Engineer} c. to Sg.{Arthur F. Sidgreaves - MD} Hs.{Lord Ernest Hives - Chair} c. to Wld. RHC.{R. H. Coverley - Production Engineer}4/MJ.21.1.38. WRAITH. The completion of drawings for Tools on the Wraith Chassis are being delayed owing to Wraith Specification not being completed. The Specification should be completed by next week-end if at all possible as all Tools must be produced by March if we are to have Chassis in Production at the time Scheduled. It is therefore important that all these should be cleared up otherwise it is going to delay Planning and Jig and Tool work in general. RHC.{R. H. Coverley - Production Engineer} | ||