Production schedule for the Bentley C-Series chassis, outlining quantities, output rates, and key deadlines.

Identifier  ExFiles\Box 142\2\  scan0290
Date  5th May 1934
  
ROY{Sir Henry Royce}6/MG5.5.34

BENTLEY CHASSIS - C.SERIES

C-A.{Mr Adams} 401-500
C-B. 501-600

Number of Chassis in Series ............. 200

Proposed Output ........................ 9½ per week
(including holidays)

Authority to proceed given ............. Wor{Arthur Wormald - General Works Manager}3/R27.4.34

First Chassis to be sent to test
week commencing ... September 17th.1934

Last Chassis to be sent to test............

Drawing Office to complete issue of
instructions week ending ..... May 5th.1934

ORDER OFFICE TO COMPLETE ISSUE OF ORDERS:-

Classes C & D, and any materials
required from overseas .. May 12th. 1934
Class B ................................ May 19th. "
Class A ................................ May 26th. "
Instruments ............................ June 2nd. "

Material to be in Stores:-

Class D (Forging Bars & Billets) ........ June 9th. "
Classes C & D .......................... June 23rd. "
Class B ................................ July 7th. "
Class A ................................ July 21st. "
Instruments ............................ July 21st. "

Material to be issued to Works, together
with instructions and production cards:

Castings made in our Foundry and Forgings
produced in our Drop Forge
Classes C & D .......................... June 16th. "
Class B ................................ July 7th. "
Class A ................................ August 4th. "
Instruments ............................ August 18th."
  
  