Works chart showing the planned weekly output of Bentley chassis from July to December 1937.
Identifier | ExFiles\Box 83\3\ scan0054 | |
Date | 15th July 1937 | |
Rm.{William Robotham - Chief Engineer} 200 WORKS CHART. Chart No. 163. RHC{R. H. Coverley - Production Engineer}/JMW.11/EMG.15.7.37. CHASSIS OUTPUT. BENTLEY CHASSIS. OUTPUT FROM ERECTING BAY TO TEST DEPT. Below we give you particulars of the programme to be worked to up to the end of December. This cancels all previous charts:- 1937. Week-ending. Weekly Output. Position on Series. July 17th 8 K.152 24th Nil. 152 Annual Holiday. 31st 8 160 Aug. 7th 8 168 14th 8 176 21st 8 184 28th 8 192 Sept. 4th 8 200 11th 8 L. 8 18th 8 16 25th 8 24 Oct. 2nd 6 30 September Holiday. 9th 8 38 16th 8 46 23rd 8 54 30th 8 62 Nov. 6th 8 70 13th 8 78 20th 8 86 27th 8 94 Dec. 4th 8 102 11th 8 110 18th 8 118 25th 8 126 | ||