Progress report on Wraith chassis parts releases, planning, ordering, and test dates for various models.

Identifier  ExFiles\Box 142\2\  scan0427
Date  24th February 1938
  
continued.... -2- RHC{R. H. Coverley - Production Engineer}/DM.{D. Munro}4/IB.24.2.38.

WRAITH CHASSIS.

Approximately 85% of the parts Released.
" 85% of the above are complete on Operation Planning.
" 75% " " " are Ordered.

The table below shows the position in regard to Releases and Ordering Times.

CHASSIS.- P.III. 101'D' Bentley. 101'M' Wraith. 31st Chassis.

Due to Test. 9.7.38. 23.7.38. 23.7.38.

Weeks from now. 19. 21. 21.

Releases Overdue. Weeks. (On 26 Weeks basis). 7. 5. 5.


RHC{R. H. Coverley - Production Engineer}/D.Munro.
  
  