Progress report on Wraith chassis parts releases, planning, ordering, and test dates for various models.
Identifier | ExFiles\Box 142\2\ scan0427 | |
Date | 24th February 1938 | |
continued.... -2- RHC{R. H. Coverley - Production Engineer}/DM.{D. Munro}4/IB.24.2.38. WRAITH CHASSIS. Approximately 85% of the parts Released. " 85% of the above are complete on Operation Planning. " 75% " " " are Ordered. The table below shows the position in regard to Releases and Ordering Times. CHASSIS.- P.III. 101'D' Bentley. 101'M' Wraith. 31st Chassis. Due to Test. 9.7.38. 23.7.38. 23.7.38. Weeks from now. 19. 21. 21. Releases Overdue. Weeks. (On 26 Weeks basis). 7. 5. 5. RHC{R. H. Coverley - Production Engineer}/D.Munro. | ||