Production schedule and material plan for the 40/50 HP Chassis, Series J.2.

Identifier  ExFiles\Box 65a\2\  scan0234
Date  16th January 1929
  
Ref: ROY{Sir Henry Royce}1/MG16.1.29

40/50 HP. CHASSIS - SERIES "J.2"
Divided into two half-series, viz:
J2.A - 5613 - 5712
J2.B - 5713 - 5812

Number of Chassis in Series ............ 200
Proposed Output ........................ Average 9 per week (including holidays)
Authority to proceed given ............. 14th January 1929
First Chassis to be sent to test week commencing ................. 24th June 1929
Last Chassis to be sent to test ............
Drawing Office to complete issue of instructions week ending ..... 19th January 1929

ORDER OFFICE TO COMPLETE ISSUE OF ORDERS:
Classes C & D, and any materials required from overseas ............. 26th January 1929
Class B ................................ 9th February "
Class A ................................ 23rd February "
Instruments ............................ 9th March "

Material to be in Stores: J2.A J2-B
Classes C & D ............. 16th March 1929 8th June 1929
Class B ..................... 30th March " 22nd June "
Class A ..................... 13th April " 22nd June "
Instruments ................. 18th May " 27th July "

Material to be issued to Works together with instructions and Production Cards:- J2.A J2-B
Castings made in ourFoundry and Forgings produced in our Drop Forge
Classes C & D ............. 16th Mar.1929
Class B ..................... 30th Mar. " 22nd June "
Class A ..................... 13th April " 6th July "
Instruments ................. 27th April " 10th Aug. "
1st June "

ENCLOSURE