Project schedule Gantt chart for the 'Left Hand Silver Phantom' model, detailing tasks assigned to individuals.

Identifier  ExFiles\Box 124\4\  scan0069
Date  29th November 1939
  
Title: LEFT HAND SILVER PHANTOM.
Timeline: NOV 27, DEC 4, DEC 11, DEC 18, DEC 25, JAN 1, JAN 8, JAN 15

Assignments:
J.{Mr Johnson W.M.} DRAPER: DASH ARrGT., BRAKE LINKAGE.
D.{John DeLooze - Company Secretary} BASTOW: STEERING TUBE, STEERING COLUMN, FRONT, FAN.
F.{Mr Friese} TARLTON: REVERSE GEAR, JACKS, PRACTICAL WIRING DIAGRAM.
W. ALLEN: EXHAUST SYSTEM, FRONT FLOOR.
J.{Mr Johnson W.M.} BURKINSHAW: PEDALS, ACC. PEDAL, BRAKE LINKAGE.
L. LEECH: ENGINE CONTROLS, DAMPER CON.
H.{Arthur M. Hanbury - Head Complaints} PEAK: HAND BRAKE LEVER, SIDE WHEEL CAR, PIPES & WIRES.
W. LOVELL: SPECIF'N, PETROL TANK, PIPES & WIRES.
H.{Arthur M. Hanbury - Head Complaints} HUNT: [No task listed]
EV.{Ivan Evernden - coachwork}: STEERING COLUMN CHANGE SPEED, INST. BOARD.

Vertical Text: CHRISTMAS HOLIDAY

Stamp and Signature Area:
ROLLS-ROYCE LTD.
PRINT ROOM
28 NOV 1939
IY
29.11.39.
  
  


Copyright Sustain 2025, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙