The test schedule for the P.2 Synchro Mesh Box and the preparation of a second unit.
Identifier | ExFiles\Box 15\5\ Scan252 | |
Date | 4th March 1932 | |
87310. To.Sg.{Arthur F. Sidgreaves - MD} From Hs.{Lord Ernest Hives - Chair} c. to Wor.{Arthur Wormald - General Works Manager} c. to E.{Mr Elliott - Chief Engineer} c. to BY.{R.W. Bailey - Chief Engineer} c. to PN.{Mr Northey} Hs.{Lord Ernest Hives - Chair}8/MJ.4.3.32. P.2 SYNCHRO MESH BOX. We will let you have a schedule of tests we propose carrying out to prove the reliability of this box, and as soon as the test has started we will send in Daily Reports as requested. Another synchro-mesh box is being prepared, but at the moment it is not possible to say when it will be completed. Hs.{Lord Ernest Hives - Chair} | ||