From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Equipment estimate for the repair of a bearing on the dynamo test rig in the Electrical Laboratory.
Identifier | ExFiles\Box 143\1\ scan0380 | |
Date | 10th November 1939 | |
To Millwrights. C to N Chambers C to Powers Dept. C Rm.{William Robotham - Chief Engineer} EQUIPMENT ESTIMATE. 1209 Requisition No. B 5412 FOR DEPT. / 479 Ref. EJJ/HC.10/WB.{Mr Brazier/Mr Bell}10.11.39. R.R. M/C No. WORKS ORDER No. 815 Req. signed by Mr. Robotham. Estimated Cost Labour. £ 3. 5. 0. Material. £ 1. 4. 6. Total. £ 4. 9. 6. Description of Work Please arrange to repair the bearing on the dynamo test rig in the Electrical Laboratory. EJJ/HC. | ||