From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Production schedule for the 40/50 HP. Chassis U2 Series, detailing quantities, key dates, and material requirements.

Identifier  ExFiles\Box 142\2\  scan0321
Date  4th December 1934
  
NOY2/MG.4.12.34

40/50 HP. CHASSIS - U2 SERIES

7139 - 7163

Number of Chassis in Series ............. 25
Proposed Output ..................... 4 per week
Authority to proceed given ............. (26th November 1934 (Ref: Wor{Arthur Wormald - General Works Manager}5/M
First Chassis to be sent to test week commencing ............. April 1st.1935
Last Chassis to be sent to test .........
Drawing Office to complete issue of instructions week ending ..... As soon as possible

ORDER OFFICE TO COMPLETE ISSUE OF ORDERS:-

Classes C & D, and any materials required from overseas ............. As soon as possible
Class B ........................... " " "
Class A ........................... " " "
Instruments ....................... " " "

Material to be in Stores:-

Class D, Forging Bars and Billets .... January 3rd.1935
Classes C & D ..................... January 19th. "
Class B ........................... February 2nd. "
Class A ........................... February 16th. "
Instruments ....................... February 16th. "

Material to be issued to Works, together with instructions and production cards:-

Castings made in our Foundry and Forgings produced in our Drop Forge
Classes C & D ..................... January 5th.1935
Class B ........................... January 26th. "
Class A ........................... February 9th. "
Instruments ....................... February 23rd. "
  
  