From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Gantt chart outlining the production schedule for the Bentley III model from 1938 to 1939.

Identifier  ExFiles\Box 97\1\  scan0204
Date  1st September 1938 guessed
  
BENTLEY III SCHEDULE
1938
JULY AUG SEPT OCT NOV DEC
1939
JAN FEB MAR APR MAY JUN JUL AUG SEP

FINAL DESIGNS.
COMPLETION OF MODA. OCT 15TH

DETAIL DRAWINGS.
PRELIMINARY SEP 30TH
FINAL MODIFICATIONS NOV 15TH

OPERATION PLANNING
PRELIMINARY SEP 30TH
FINAL MODIFICATIONS NOV 30TH

COSTING
PRELIMINARY OCT 31ST
DETAIL DEC 31ST

SPECIAL MACHINE EQUIPMENT INSTRUCTIONS.
[Bar end date] NOV 30TH

JIG & TOOL INSTRUCTIONS.
CLASS 'A' NOV 30TH
CLASS 'B' MAR 31ST
LONG DISTANCE JIGS FOR MAJOR PARTS
SMALL JIGS & TOOLS

JIGS, TOOLS, & SPECIAL MACHINE EQUIPMENT.
CLASS 'A' JAN 31ST
CLASS 'B' APR 30TH
TO BE MANUFACTURED & PROVED

MATERIAL FOR EXP. & SHOW CHASSIS TO BE RELEASED BY D.O.
[Start date] SEP 1ST
[End date] FEB 28TH

PRODUCTION OF EXP. CHASSIS.
[Start date] JAN 1ST
[End date] MAR 31ST

MATERIAL FOR PROD'N CHASSIS TO BE ORDERED.
[Start date] FEB 18TH
[End date] APR 22ND

PRODUCTION OF SHOW CHASSIS.
[Start date] MAR 1ST
[End date] JUN 30TH

DELIVERY OF SHOW CHASSIS.
[Start date] JUN 1ST
[End date] JUL 31ST

CHASSIS TO TEST AT RATE OF 16 PER WEEK.
[Start date] SEP 1ST

PRODUCTION OF BENTLEY II CHASSIS CEASES.
[Start date] JAN 1ST
[End date] MAR 31ST
  
  