Cover note for a fortnightly report on rechassis design progress, noting delays due to structural work and staff relocation.
Identifier | ExFiles\Box 133\4\ scan0100 | |
Date | 4th December 1939 | |
SECRET 1125 TO. Rm.{William Robotham - Chief Engineer} c. Rm{William Robotham - Chief Engineer}/Grys Ev.{Ivan Evernden - coachwork}1/4.12.39 RECHASSIS DESIGN Attached is the fortnightly report on the progress of chassis design and detail work. We regret that the rate of progress may have been slowed down somewhat due to structural work going on, and also the removal of staff to the Annexe. | ||