Work programme for a Chassis S/C Unit, detailing component fitting and testing schedules due to a delay.


Identifier  ExFiles\Box 133\1\  scan0194
Date  3rd May 1937
  
1129

To HPS. {Horace Percy Smith - Experimental Factory Mgr}
c. to Rm {William Robotham - Chief Engineer} /Swdl. {Len H. Swindell}
c. to E {Mr Elliott - Chief Engineer} /PSN.

Rm {William Robotham - Chief Engineer} /Ed. {J. L. Edwards} 8/JH.3.5.37

Chassis S/C. Unit.

Running time for week ending 1st. May 1937 - 16½ hours.
Fitting time for week ending 1st. May 1937 - 31½ hours.

Due to unexpected delays the inclined alum head to LeC.5368 has been held up and we are therefore substituting the following programme.

Work to be done. | Time.
--- | ---
Power and detonation on exhaust plug on deturbulated No. 2 head. | 1 day.
SHOP. Fit alum head to RS. {Sir Henry Royce's Secretary} 315. |
Detonation with alum head and cooled exhaust valve | ½ day.
SHOP. Fit large valve block to Ex.18336 with solid exhaust valve and No.2 head. In the meantime the alum head should be modified to take a 1.850" valve to RS. {Sir Henry Royce's Secretary} 317. |
Running in for new block. |
Power and detonation in standard valve timing | 2 days.
Power on E.O. 51°E. {Mr Elliott - Chief Engineer} E.C. T.D.C. |
SHOP. Fit alum head with large inlet valve on standard block Ex.17163, using cooled exhaust valve to SCT.55. |
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙