From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Bi-weekly progress report for the Chassis Section.
Identifier | ExFiles\Box 133\4\ scan0289 | |
Date | 25th March 1942 | |
1125 To Hp. from Ev{Ivan Evernden - coachwork}/JD.{J. Draper - Frames} Copy to Ev.{Ivan Evernden - coachwork} Rm{William Robotham - Chief Engineer}/SJH. Ev{Ivan Evernden - coachwork}/JD.{J. Draper - Frames}7/SL.25.3.42. PROGRESS REPORT CHASSIS SECTION For the two weeks ending 23rd March, 1942. WORK COMPLETED. All the details for the large B.V. petrol tank have been completed and handed to Rm{William Robotham - Chief Engineer}/HH. for issue. WORK IN HAND. All the designs mentioned in memo Ev.{Ivan Evernden - coachwork}9/JH.30.1.42 are still unfinished. The following extra design is in hand:- Clutch housing to adapt Austin 8 gearbox to the Myth engine. Ev{Ivan Evernden - coachwork}/JD.{J. Draper - Frames} | ||