Work programme for a supercharged chassis unit, detailing running times and a schedule of modifications and tests.

Identifier  ExFiles\Box 133\1\  scan0166
Date  22th February 1937
  
1/29
HPS{Horace Percy Smith - Experimental Factory Mgr} from Rm{William Robotham - Chief Engineer}/Ed{J. L. Edwards}
c to E/PSN
Rm{William Robotham - Chief Engineer}/Ed{J. L. Edwards}11/M.22.2.37.
S/C Chassis Unit.
Running time for week ending 20th Feb. 1937 - 15 1/2 hours.
Fitting time " " " - 23 "
Programme for week ending 27th February 1937.
Work to be done. Time.
Carried forward:- Complete fitting of No. 1 Head (LeC 4075)
Run power and detonation curves. 1 1/2 days.
SHOP:- Fit alum. high power head to RS{Sir Henry Royce's Secretary}315 incorporating high lift rocker and 1.750" dia. inlet valve.
Power and detonation curves. 1 1/2 days.
SHOP:- Remove .048" gasket and fit a new one of 33 gauge (.010" thick) to give a C.R. of approximately 6.60. This gasket will have to be made.
Power and detonation tests. 1 day.
SHOP:- The C.R. is now to be raised to 7.0 : 1 and instructions will be issued as soon as it is possible to state how much is to be machined off the head.
Power and detonation tests. 1 1/2 days.