Work programme for a supercharged chassis unit, detailing running times and a schedule of modifications and tests.


Identifier  ExFiles\Box 133\1\  scan0166
Date  22th February 1937
  
1/29
HPS {Horace Percy Smith - Experimental Factory Mgr} from Rm {William Robotham - Chief Engineer} /Ed {J. L. Edwards}
c to E {Mr Elliott - Chief Engineer} /PSN
Rm {William Robotham - Chief Engineer} /Ed {J. L. Edwards} 11/M.22.2.37.
S/C Chassis Unit.
Running time for week ending 20th Feb. 1937 - 15 1/2 hours.
Fitting time " " " - 23 "
Programme for week ending 27th February 1937.
Work to be done. Time.
Carried forward:- Complete fitting of No. 1 Head (LeC 4075)
Run power and detonation curves. 1 1/2 days.
SHOP:- Fit alum. high power head to RS {Sir Henry Royce's Secretary} 315 incorporating high lift rocker and 1.750" dia. inlet valve.
Power and detonation curves. 1 1/2 days.
SHOP:- Remove .048" gasket and fit a new one of 33 gauge (.010" thick) to give a C.R. of approximately 6.60. This gasket will have to be made.
Power and detonation tests. 1 day.
SHOP:- The C.R. is now to be raised to 7.0 : 1 and instructions will be issued as soon as it is possible to state how much is to be machined off the head.
Power and detonation tests. 1 1/2 days.
Contd.
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙