From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Production schedule for chassis testing, detailing weekly output and series positions for different models.

Identifier  ExFiles\Box 142\3\  scan0361
Date  4th October 1937
  
Rm.{William Robotham - Chief Engineer}
P. 1206o.
RHC{R. H. Coverley - Production Engineer}/JMW.1/EMG.4.10.37.

SCHEDULE OF CHASSIS TO TEST.

Herewith details of the Programme to be worked up to week-ending January 1st 1938.

This cancels all previous Output Schedules.

1937.

MONTH. WEEK-ENDING. 25/30 HP. Weekly Output. Series Position. BENTLEY. Weekly Output. Series Position. PHANTOM III. Weekly Output. Series Position.
Oct. 9th 8 R.{Sir Henry Royce} 11 8 L. 38 4 C.149
16th 8 19 8 46 4 153
23rd 8 27 8 54 4 157
30th 8 35 8 62 4 161
Nov. 6th 8 43 8 70 4 165
13th 8 51 8 78 4 169
20th 8 59 8 86 4 173
27th 8 67 8 94 4 177
Dec. 4th 8 75 8 102 4 181
11th 8 83 8 110 4 185
18th 8 91 8 118 4 189
25th 8 99 8 126 4 193

1938.
Jan. 1st 8 107 8 134 4 197
  
  