Production schedule for the Phantom III C.Series chassis detailing quantities, timelines, and material requirements.

Identifier  ExFiles\Box 142\2\  scan0376
Date  22th September 1936
  
ROY{Sir Henry Royce}2/W022.9.36

PHANTOM III - C.SERIES

C-A.{Mr Adams} 413-512
C-B. 513-612

Number of chassis in Series .......... 200
Proposed Output .................... 10 per week including holidays
Authority to proceed ............... Hy{Tom Haldenby - Plant Engineer}2/R4.9.36
First chassis to be sent to test week commencing ...... March 8th.1937
Drawing Office to complete issue of instructions week ending....... September 12th.1936

Order Office to complete issue of orders:

Classes C & D and any materials required from overseas ......... September 26th.1936
Class B .......................... October 3rd. "
Class A .......................... October 17th. "
Instruments ...................... October 24th. "

Material to be in Stores:

Class D (Forging Bars & Billets) ... November 21st.1936
Classes C & D .................... December 5th. "
Class B .......................... January 5th.1937
Class A .......................... January 5th. "
Instruments ...................... January 9th. "

Material to be issued to Works, together with instructions and production cards:-

Castings made in our Foundry and Forgings produced in our Drop Forge.. November 28th.1936
Classes C & D .................... December 19th. "
Class B .......................... January 8th.1937
Class A .......................... January 16th. "
Instruments ...................... February 6th. "

ENCLOSURE No 860 "JUSTSO"
  
  