Weekly chassis output schedule for Bentley models from the erecting bay to the test department for 1937.
Identifier | ExFiles\Box 142\3\ scan0177 | |
Date | 8th April 1937 | |
Rm.{William Robotham - Chief Engineer} 1204 Chart No. 154 RHC{R. H. Coverley - Production Engineer}/JMW.1/EMG.8.4.37. CHASSIS OUTPUT. BENTLEY CHASSIS. OUTPUT FROM ERECTING BAY TO TEST DEPT. Below we give you particulars of the programme to be worked to up to the end of September. This cancels all previous charts.- 1937. Week-ending. Weekly Output. Position on Series. April' 10th 12 K.{Mr Kilner} 10 17th 12 22 24th 12 34 May 1st 12 46 8th 12 58 15th 10 68 Coronation Holiday. 22nd 8 76 Whitsuntide Holiday. 29th 12 88 June 5th 12 100 12th 12 112 19th 12 124 26th 12 136 July 3rd 12 148 10th 12 160 17th 11 171 ) Annual ) Holiday. 24th Nil. 171 ) 31st 12 183 Aug. 7th 12 195 14th 8 L. 3 21st 8 11 28th 8 19 Sept. 4th 8 27 11th 8 35 18th 8 43 25th 7 50 September Holiday. | ||