Progress report on the 'Continental' project listing completion dates for various components.

Identifier  ExFiles\Box 92\6\  scan0063
Date  15th December 1936
  
CONTINENTAL.

Clutch and case completed 19th
Engine ................ 19th
Radiator finished ....... 21st
Wraith wheel movement ... 21st
Gearbox ................ Christmas.
Steering parts. Thin section ................ All parts completed.
Exhaust System .......... Christmas.
Brake Gear .............. Completed.

Packard balance weight crank Lightened Jan. 7th completed.

Jack brackets promised Dec. 16th.

Over-speed gears.
  
  