50-hour test run of the Bentley III bumper chassis, detailing spring performance and proposed revisions.


Identifier  ExFiles\Box 119\1\  scan0106
Date  17th May 1938
  
1024

To By. {R.W. Bailey - Chief Engineer} from Rm {William Robotham - Chief Engineer} /AFM. {Anthony F. Martindale}
c. Da. {Bernard Day - Chassis Design}

Rm {William Robotham - Chief Engineer} /AFM. {Anthony F. Martindale} 4/MH. {M. Huckerby} 17.5.38.

BENTLY III BUMPER CHASSIS.

We attach a list of the various parts of the chassis which failed during a 50 hour run of the rear end on 3" cams.

The springs being run were 4" deflection 5 leaf Woodhead springs. These stood up rather longer on the average than the 5 leaf springs that we have run on B.II, but not so long as the standard 9 leaf springs.

The next springs we will run will be 5 leaf 5 1/2" initial deflection springs, as we find the lower rating desirable on the car. The lower rating springs are likely to stand up longer in service: they have 8 leaves.

The bijur pipe layout, rear dampers and their brackets and the gear box mounting are all being revised.

The threaded shackles at the rear of the springs, the silentbloc at the front end of the springs, and the frame, gave no trouble.

The rear end of the chassis, being conventional, is not likely to give serious trouble and we will concentrate on increasing the reliability of the front end.

Rm {William Robotham - Chief Engineer} /AFM. {Anthony F. Martindale}
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙