Requesting an update on the development and testing timeline for the 3 1/2-Litre Bentley power unit.


Identifier  ExFiles\Box 3\6\  06-page131
Date  25th February 1934
  
H3
X4553

To E. {Mr Elliott - Chief Engineer} from Sg. {Arthur F. Sidgreaves - MD}
Copy to Wor. {Arthur Wormald - General Works Manager} Hs. {Lord Ernest Hives - Chair}
HY. {Tom Haldenby - Plant Engineer} Bn. {W.O. Bentley / Mr Barrington} Ev. {Ivan Evernden - coachwork}

re 3 1/2-Litre Bentley.

Sg {Arthur F. Sidgreaves - MD} 21/25.2.34

Referring to E.6/HP.29.1.34 I note that the development of the Bentley power unit is waiting until the Experimental Dept. are in a position to give us some results from the single cylinder chassis test unit you have instructed and the new type of head.

I should be glad if Hs. {Lord Ernest Hives - Chair} will say when he anticipates being in a position to do this.

With regard to the second paragraph I gather that this is quite a separate and distinct test from the above, i.e. the running of an engine in a car with four bearings only, and here again I should be glad if Hs. {Lord Ernest Hives - Chair} will say how soon he expects to be able to do this.

Sg. {Arthur F. Sidgreaves - MD}
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙