From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Car's delay from the coachbuilders, required modifications including a new clutch and bumper, and urgent work on a Bentley.

Identifier  ExFiles\Box 82\3\  scan0054
Date  9th November 1934
  
To Sg.{Arthur F. Sidgreaves - MD} from Hs{Lord Ernest Hives - Chair}/Rm.{William Robotham - Chief Engineer}

Hs{Lord Ernest Hives - Chair}/Rm.{William Robotham - Chief Engineer}13/KW.9.11.34.

5-B-IV.

Replying to Sg.{Arthur F. Sidgreaves - MD}3/E.{Mr Elliott - Chief Engineer} 8.11.34.

We have not yet received this car from the Coachbuilders. We understand that you are to see it on Tuesday next to comment on the front wing appearance.

When the car reaches the Works we anticipate that it will be at least 5 or 6 weeks before it is ready to go to France. It will be fitted with a completely new design of clutch which we have never previously tried, it will also have to be fitted with the new design of Bumper Bar, the drawings for which have yet to be completed.

The lead bronze big end bearings, which we consider perhaps to be the most urgent job on the Bentley, will have been tested on the 20/25, 21-G-IV.

Hs{Lord Ernest Hives - Chair}/Rm.{William Robotham - Chief Engineer}
  
  