Production schedule for the 25/30 HP. Chassis - N.2 Series.


Identifier  ExFiles\Box 142\2\  scan0357
Date  7th April 1936
  
ROY {Mr H. Royce - Buyer} 1/MG7.4.36

25/30 HP. CHASSIS - N.2 SERIES

N2.A 7107-7206
N2.B 7207-7306

Number of Chassis in Series ............. 200

Proposed Output ........................ 15 per week (including holidays)

Authority to proceed ................... Wor {Arthur Wormald - General Works Manager} 5/R23.3.36

First chassis to be sent to test week commencing ............. September 14th.1936

Drawing Office to complete issue of instructions week ending.. April 4th.1936

ORDER OFFICE TO COMPLETE ISSUE OF ORDERS:-

Classes C & D and any materials required from Overseas ....... April 11th.1936
Class B ................................ April 18th. "
Class A ................................ April 25th. "
Instruments ............................ April 25th. "

Material to be in Stores:-

Class D (Forging Bars & Billets) ......... May 30th.1936
Classes C & D .......................... June 13th. "
Class B ................................ June 27th. "
Class A ................................ July 11th. "
Instruments ............................ July 11th. "

Material to be issued to Works, together with instructions and Production Cards:-

Castings made in our Foundry and Forgings produced in our Drop Forge ............ June 6th. 1936
Classes C & D .......................... June 27th. "
Class B ................................ July 11th. "
Class A ................................ July 25th. "
Instruments ............................ August 8th. "
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙