Delay in fitting a Barker body to chassis 18-EX due to incorrect dimensions from the coachbuilder.

Identifier  WestWitteringFiles\T\November1928\  Scan054
Date  26th November 1928
  
To R.{Sir Henry Royce} from Hs.{Lord Ernest Hives - Chair}
c. to BJ. Wor.{Arthur Wormald - General Works Manager}
c. to DA.{Bernard Day - Chassis Design} E.{Mr Elliott - Chief Engineer}
c. to BY.{R.W. Bailey - Chief Engineer}

ORIGINAL

Hsl/LG26.11.28.

'SS{S. Smith}' CAR. X7770 X1698

It is going to take us longer than we anticipated to fit the Barker body to chassis 18-EX owing to the fact that Barkers disregarded the dimensions given on the drawing. DA{Bernard Day - Chassis Design}/EV.{Ivan Evernden - coachwork} will explain the difficulties we have had.

We expect now to have the car all completed by the weekend and hope to arrive at WW. with it on Tuesday next Dec.4th.

Very good progress is being made with a further chassis, and a bump chassis of this type.

Hs.{Lord Ernest Hives - Chair}
  
  