Cost estimation and comparison for introducing a new part, including tooling costs for the 'G' series chassis.

Identifier  ExFiles\Box 136\1\  scan0170
Date  12th August 1935
  
Est. cost of extra jigs, tools and equipment (Sft{Mr Swift}/Ws.12.8.35) £178.0.0

Could be brought on to production at 1st chassis in "G" series, (Sft{Mr Swift}/GH.12.8.35) without scrap.

Material Labour Charges Total
£-s-d £-s-d £-s-d £-s-d
Cost of Old Part. 2-18-6 3-0-7 4-10-11 10-10-0
Cost of New Part. 3-1-0 +3-0-4 4-10-6 10-11-10
Nett Increase. £- 1-10

+ Exclusive of any saving which may result in gear quietening.
  
  