From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Cost estimation and comparison for introducing a new part, including tooling costs for the 'G' series chassis.
Identifier | ExFiles\Box 136\1\ scan0170 | |
Date | 12th August 1935 | |
Est. cost of extra jigs, tools and equipment (Sft{Mr Swift}/Ws.12.8.35) £178.0.0 Could be brought on to production at 1st chassis in "G" series, (Sft{Mr Swift}/GH.12.8.35) without scrap. Material Labour Charges Total £-s-d £-s-d £-s-d £-s-d Cost of Old Part. 2-18-6 3-0-7 4-10-11 10-10-0 Cost of New Part. 3-1-0 +3-0-4 4-10-6 10-11-10 Nett Increase. £- 1-10 + Exclusive of any saving which may result in gear quietening. | ||