From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).
Chassis production rates, investment in a moulding plant, and sales policy.

Identifier  ExFiles\Box 18\6\  Scan353
Date  21th September 1922 guessed
  
-5-

Chassis will be delivered to Test at rate of 5 per week by end of November and 10 per week by early in January (to Test), 20 per week to Test four months from present date, in view of permission having been given to order material as required, and the spending of £3,300 in moulding plant; this plant would do all moulding too for 10 - 40/50 chassis per week.

Works were instructed to give Sales 20 chassis per week as soon as possible.

Chassis will be sold as they are made, i.e. Works will not be asked to alter steerings etc. to suit customers, a customer will have to wait until a chassis of his type comes along.
  
  