Progress update on the Phantom engine's new aluminium head and cylinders, and the EAC-Vll chassis.

Identifier  WestWitteringFiles\P\2July1926-September1926\  Scan109
Date  30th August 1926
  
To R.{Sir Henry Royce} from Hs.{Lord Ernest Hives - Chair}
c. to BJ. Wor.{Arthur Wormald - General Works Manager}
c. to E.{Mr Elliott - Chief Engineer} DA.{Bernard Day - Chassis Design}
c. to BY.{R.W. Bailey - Chief Engineer}

ORIGINAL

Hs{Lord Ernest Hives - Chair}7/LG30.8.26.

EAC-Vll. X7770
X.7050

We anticipate it will be 4 or 5 weeks before we have a Phantom engine running with the new aluminium head and cylinders. It will be at least 8 or 9 weeks before an EAC-Vll chassis can be completed.

The patterns for the head and cylinders are nearing completion.

A number of the outstanding parts for this chassis are given in BY1/H28.8.26 progress report.

Hs.{Lord Ernest Hives - Chair}
  
  