Production schedule for 20/25-HP Chassis - Series 'S'.

Identifier  ExFiles\Box 142\2\  scan0119
Date  5th March 1930
  
Ref:- ROY{Sir Henry Royce}6/MG5.3.30

20/25-HP CHASSIS - SERIES "S".
S-A.{Mr Adams} 3401-3500..
S-B. 3501-3600..

Number of Chassis in Series ................... 200.
Proposed Output ............................... Average 8 per week including holidays.
Authority to proceed given .................... Sg{Arthur F. Sidgreaves - MD}20/E.26.2.30.
First Chassis to be sent to test week commencing ... 25th August 1930.
Last Chassis to be sent to test ...............
Drawing Office to complete issue of instructions week ending ... 15th March 1930.

ORDER OFFICE TO COMPLETE ISSUE OF ORDERS:-
Classes C & D, and any materials required from overseas ............. 22nd March 1930.
Class B ................................ 29th March "
Class A ................................ 12th April "
Instruments ............................ 19th April "

Material to be in Stores:-
S-A.{Mr Adams} S-B.
Class D (Billet & Forging Bars) ...... 3rd May 1930. -
Classes C & D ........................ 17th May " -
Class B .............................. 24th May " 9th August 1930.
Class A .............................. 7th June " 23rd August "
Instruments .......................... 12th July 20th Sept. "

Material to be issued to Works, together with instructions and production cards:-

Castings made in our Foundry and Forgings produced in our Drop Forge
S-A.{Mr Adams} S-B.
17th May 1930. -
24th May " -
7th June " 16th August 1930.
21st June " 30th August "
26th July 4th Oct. "

[Red Stamp]
ENCLOSURE
No 169
"JUSTSO"
  
  