Progress report outlining actions and deadlines for the Phantom III Continental project.
| Identifier | ExFiles\Box 92\6\ scan0050 | |
| Date | 5th November 1936 | |
| P.111. CONTINENTAL. Y 300b 5.11.36. MAGNESIUM CASTINGS. Gry.{Shadwell Grylls} to have settled the position by the 10th. Also note from Walker. FRAME. When dealing with Wraith frame Gry.{Shadwell Grylls} will clear up outstanding Phantom lll. details. REAR BRAKE JOB. Promise on 10th. [Handwritten] All to be complete by 25th FRONT SUSPENSION. Castings well on. Promise Bump set first. STEERING. Promise next week. [Handwritten] end of month 28th JACKS. Promise next week. Gry.{Shadwell Grylls} [Handwritten] 3 weeks RADIATOR MATRIX. Cassel promise from Steadman. CRANKSHAFT. Details to be available for the 10th. WRAITH WHEEL MOVEMENT. Report on situation on 10th. Rm.{William Robotham - Chief Engineer} | ||