Progress report outlining actions and deadlines for the Phantom III Continental project.

Identifier  ExFiles\Box 92\6\  scan0050
Date  5th November 1936
  
P.111. CONTINENTAL. Y 300b 5.11.36.

MAGNESIUM CASTINGS.
Gry.{Shadwell Grylls} to have settled the position by the 10th.
Also note from Walker.

FRAME.
When dealing with Wraith frame Gry.{Shadwell Grylls} will clear up
outstanding Phantom lll. details.

REAR BRAKE JOB.
Promise on 10th.
[Handwritten] All to be complete by 25th

FRONT SUSPENSION.
Castings well on. Promise Bump set first.

STEERING.
Promise next week.
[Handwritten] end of month 28th

JACKS.
Promise next week. Gry.{Shadwell Grylls}
[Handwritten] 3 weeks

RADIATOR MATRIX.
Cassel promise from Steadman.

CRANKSHAFT.
Details to be available for the 10th.

WRAITH WHEEL
MOVEMENT.
Report on situation on 10th.


Rm.{William Robotham - Chief Engineer}
  
  