Cost estimate and production plan for new tooling for standardisation of parts on the Phantom II 'C' series chassis.
| Identifier | ExFiles\Box 171\2\ img309 | |
| Date | 11th June 1921 | |
| PHANTOM II STANDARDISATION of PARTS Estimated cost of new tools £108.0.0. Could be brought on to production at the 101st chassis in "C" series (without scrap). (Faint mirrored text decodes as: The objection is that a set of parts are fitted to...) --- Cost Breakdown Table (mirrored) --- Columns: MATERIAL, LABOUR, CHARGES, TOTAL (Values are heavily distorted and illegible) --- Approvals Table --- (Column headers INITIAL, DATE, REMARKS are mirrored) INITIALS | DATES | REMARKS (mirrored) SG {Arthur F. Sidgreaves - MD} | .28 HS {Lord Ernest Hives - Chair} | .0 D | .3 E | .11.6.21 | passed DA {Bernard Day - Chassis Design} | .13.6.21 | passed BY | .15.6.21 | passed KXXR BHC MX {John H Maddocks - Chief Proving Officer} | .11.6.21 | passed RM {William Robotham - Chief Engineer} | .13.6.21 | passed (Mirrored note at bottom: Tool cost will be £60.0.0. net.) | ||
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).