Comparison of allowed versus actual production times for various chassis models across different departments.

Identifier  ExFiles\Box 148\5\  scan0130
Date  21th December 1936
  
COPY.

To Hs{Lord Ernest Hives - Chair} from G/Rb.{R. Bowen}
c. to RHC.{R. H. Coverley - Production Engineer}

G/Rb.{R. Bowen}11/52/W.211236.

PRODUCTION TIMES FOR CHASSIS.

The statement below shows the time allowances and the average actual times under the departmental heads used in the financial accounts. The average actual times are obtained using the latest bonus earnings and where possible we have taken chassis sections only, but where departments are producing both chassis and aero work, viz: Automatics, Gear Cutters etc. we have, of necessity, had to apply the bonus earnings for both products.

Average Time Allowed Actual Time
Bonus Hours Hours

Machining
Bentley )
25/30 ) 51.84% 1835 900
Phantom III ) 2006 985
3315 1627

Fitting
Bentley )
25/30 ) 56.78% 1388 647
Phantom III ) 1551 723
2660 1245

Foundry
Bentley . )
25/30 ) 55.75% 228 107
Phantom III ) 247 116
565 267

Drop Forge
Bentley )
25/30 ) 45.38% 35 18
Phantom III ) 49 26
50 26

Tin & Coppersmith
Bentley )
25/30 ) 49.92% 234 117
Phantom III. 268 134
391 196

Testing
Bentley )
25/30 ) 54.02% 161 77
Phantom III 192 92
250 120

TOTALS: Bentley 3881 1866
25/30 4313 2076
Phantom III. 7231 3481
  
  