Cost and production analysis for the standardization of a shock absorber for control.


Identifier  ExFiles\Box 95\4\  scan0098
Date  15th April 1937
  
COMPLETED A.W.I. No. 7172. B.H. 257 S.L.
PHANTOM III. STANDARDISATION of PARTS.

Date: 15.4.37.
Ref No.: SAC. on X
Drawing No.: F.950
Part No.: P.804

SHOCK ABSORBER FOR CONTROL. "CONTROL"
To overcome the stiffness of the "A" Series.
Origin: J.E. Ellor

Estimated Cost of new Tools £108. 0. 0.
Could be brought on to production at the 101st chassis in "C" Series (without scrap).

Cost Table:
Headers: MATERIAL s. d. {John DeLooze - Company Secretary} ; LABOUR s. d. {John DeLooze - Company Secretary} ; CHARGES s. d. {John DeLooze - Company Secretary} ; TOTAL s. d. {John DeLooze - Company Secretary}
Cost of Old Part: 8 4; 2 6; 0 9; 11 7
Cost of New Part: 9 0; 5 3; 8 4 1/2; 1 2 7 1/2
Difference (Increase): 8; 2 9; 7 7 1/2; 11 0 1/2

Saving from both Depts. that above is correct.

Approvals Table:
REMARKS | DATE | INITIALS | S.O. No.
Agreed. H.S. | 16.4.37 | H.S. | 98
Agreed. O.C. | 16.4.37 | O.C.
Agreed. E.H. | 16.4.37 | E.H.
Agreed. A.G. | 24.4.37 | A.G.
Agreed. By V.P. | 12.5.37 | V.P.
Agreed. D.R.H. | CH.O. 1-6-37 | DRH | 847
Agreed. M.X. | 12.5.37 | M.X.

Tool costs will be £130.0.0. not £108.0.0.

STAMP: WORKS SANCTIONED 17 MAY 1937
  
  
From the Rolls-Royce experimental archive: a quarter of a million communications from Rolls-Royce, 1906 to 1960's. Documents from the Sir Henry Royce Memorial Foundation (SHRMF).


Copyright Sustain 2026, All Rights Reserved.    whatever is rightly done, however humble, is noble
An unhandled error has occurred. Reload 🗙